Here’s a real enterprise-grade Oracle migration checklist (used for AIX → RHEL, on-prem → cloud, or platform modernization). It is structured the way large banks, telecoms, and ERP environments execute migrations safely.


1. Governance & project readiness

Business alignment

  • ☐ Migration scope clearly defined (DB only / full stack / apps included)
  • ☐ Downtime window agreed (RTO/RPO targets defined)
  • ☐ Critical business processes identified
  • ☐ Stakeholders and approvers mapped

Project controls

  • ☐ Migration strategy approved (GoldenGate / RMAN / Data Pump)
  • ☐ Rollback strategy documented and tested
  • ☐ Change management approvals (CAB) completed
  • ☐ Risk register created

2. Source system assessment (AIX / legacy)

Oracle environment

  • ☐ Oracle version & patch level documented
  • ☐ Database size (datafiles, redo, temp) analyzed
  • ☐ Character set verified (prefer AL32UTF8)
  • ☐ Endianness identified (AIX = Big Endian)

Workload analysis

  • ☐ AWR baseline captured (peak + off-peak)
  • ☐ Top SQL queries identified
  • ☐ Wait events analyzed
  • ☐ Batch windows mapped

Dependencies

  • ☐ Application integrations mapped (ERP, APIs, ETL)
  • ☐ External jobs (cron, Control-M, scripts)
  • ☐ Linked servers / DB links identified

3. Target architecture design (RHEL / Linux)

Infrastructure

  • ☐ Server sizing validated (CPU, RAM, IOPS)
  • ☐ Storage design confirmed (ASM / XFS / NVMe / SAN)
  • ☐ Network bandwidth for replication confirmed

Oracle setup

  • ☐ Oracle version compatibility confirmed
  • ☐ Grid Infrastructure installed (if RAC/ASM)
  • ☐ HugePages configured
  • ☐ Kernel parameters tuned (sysctl.conf)

HA/DR design

  • ☐ Data Guard design (if required)
  • ☐ RAC decision (single vs cluster)
  • ☐ Backup strategy (RMAN on Linux)

4. Migration strategy selection

Choose based on downtime requirement:

  • ☐ Data Pump (low complexity, high downtime)
  • ☐ RMAN cross-platform (medium complexity)
  • ☐ GoldenGate (near-zero downtime – enterprise standard)

5. Data migration preparation

Schema readiness

  • ☐ Primary keys exist on all tables
  • ☐ Unsupported objects identified
  • ☐ LOB handling validated
  • ☐ Materialized views strategy defined

Pre-seeding data

  • ☐ RMAN backup or Data Pump export completed
  • ☐ Target database restored successfully
  • ☐ Initial data consistency validated

6. Replication setup (if GoldenGate used)

Source (AIX)

  • ☐ Extract process configured
  • ☐ Archive log mode enabled
  • ☐ Supplemental logging enabled

Target (RHEL)

  • ☐ Replicat configured
  • ☐ Trail files processing verified
  • ☐ Initial sync completed

Validation

  • ☐ Lag monitoring enabled
  • ☐ Transaction consistency verified
  • ☐ Conflict detection rules defined

7. Application readiness

Compatibility

  • ☐ JDBC/OCI drivers tested
  • ☐ Connection strings updated in test
  • ☐ Timezone alignment verified
  • ☐ Character encoding consistency checked

Code validation

  • ☐ PL/SQL procedures tested
  • ☐ Shell scripts updated (AIX → Linux commands)
  • ☐ File path changes validated

8. Performance benchmarking

  • ☐ AWR baseline captured on AIX
  • ☐ Load testing on RHEL completed
  • ☐ SQL execution plans compared
  • ☐ I/O latency measured
  • ☐ CPU scaling validated (NUMA awareness)

9. Cutover planning

Pre-cutover checklist

  • ☐ Final replication lag = 0
  • ☐ All stakeholders on standby
  • ☐ Change freeze implemented
  • ☐ Backup taken immediately before cutover

Cutover steps

  • ☐ Stop application writes on source
  • ☐ Final sync completed
  • ☐ Switch traffic (DNS / load balancer / TNS)
  • ☐ Validate transactions in target system

10. Rollback plan (mandatory)

  • ☐ Source system kept intact
  • ☐ Reverse replication plan (if needed)
  • ☐ Application fallback tested
  • ☐ DNS rollback procedure ready
  • ☐ Decision point defined (go/no-go)

11. Post-migration validation

Data integrity

  • ☐ Row count validation
  • ☐ Financial reconciliation (if applicable)
  • ☐ Critical tables verified

Application validation

  • ☐ End-to-end business flows tested
  • ☐ Integration systems verified
  • ☐ Batch jobs running correctly

Performance checks

  • ☐ AWR comparison (before vs after)
  • ☐ CPU, memory, I/O monitoring
  • ☐ Query performance stability

12. Optimization phase

  • ☐ Gather new optimizer statistics
  • ☐ Adjust SGA/PGA sizing
  • ☐ Tune redo logs / I/O subsystem
  • ☐ Enable compression if applicable
  • ☐ Revisit partitioning strategy

13. Operations & monitoring setup

  • ☐ Enterprise monitoring (OEM / Prometheus / Grafana)
  • ☐ Alerting configured
  • ☐ Backup jobs scheduled
  • ☐ DR drills planned
  • ☐ Access control reviewed (security hardening)

14. Decommissioning legacy system

  • ☐ AIX system kept in read-only mode (initial period)
  • ☐ Final sign-off from business
  • ☐ Archive backup stored securely
  • ☐ Decommission plan approved
  • ☐ Licensing cleanup (if applicable)

15. Common enterprise pitfalls

⚠ Skipping workload baseline (AWR)
⚠ Ignoring hidden batch jobs
⚠ Underestimating network lag in GoldenGate
⚠ Missing primary keys for replication
⚠ Not testing rollback
⚠ Carrying AIX tuning assumptions to Linux


16. Golden rule

“Successful Oracle migration is not about moving data — it is about preserving business continuity under a new architecture.”